BMW Daeninck Oudenaarde

Total site area: 11,700 m² Total floor area: 9,300 m² Date of commencement of the works: March 2009 End date of the works: inauguration January 2010 Redevelopment and expansion of an old textile factory and office buildings to showrooms for BMW and MINI and associated offices, workshops, body shop and second hand car showroom. Project description: In 2009, BMW and Mini dealership Daeninck NV built a new branch along the Westerring in Oudenaarde. The company purchased an old mill and converted it into an 8,800m² branch for workshops and a showroom. The old mill was a large, enclosed...